1852.234-1 NASA FAR Supplement Notice of Earned Value Management System Clause – dated April 2015
This FAR clause requires that at the time of solicitation, a contractor submit documentation that a Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EIA-748. If the contractor does not have an EVM system that is in compliance with the EIA-748, the contractor must submit a comprehensive plan to achieve compliance with the 32 guidelines. This clause also requires that major subcontractors be identified and that the contractor and the Government agree to the subcontractors selected for application of the EVMS guidelines.