Integrated Program Management Report (IPMR) : Humphreys & Associates

Proudly Serving the EVM Community for 44 Years.
The Leader in Earned Value Management Consulting and Training

Integrated Program Management Report (IPMR)


The Integrated Program Management Report (IPMR) as described in Data Item Description DI-MGMT-81861 is a contractually required report to the customer per the Department of Defense Instruction 5000.02. It was issued June 20, 2012, and supersedes the Contract Performance Report defined in Data Item Description (DID) DI-MGMT-81466A. The IPMR is normally prepared each month to formally provide technical, schedule and cost status information for company project management and for the government customer on major projects (typically $20M or more or as defined in the contract). The purpose of the IPMR is to provide early identification of problems that may have significant cost, schedule and/or technical impacts, and report the effects of management actions and project status information for use in making and validating management decisions.

The report nominally consists of seven formats, four contain data that measure the contractors' cost and schedule performance a fifth that addresses problem analysis, corrective action plans and technical, schedule and cost impact explanations, a sixth that is the contractor's Integrated Master Schedule, and the seventh is an Electronic History and Forecast File.

  • Format 1 includes cost and schedule performance data by product-oriented Work Breakdown Structure (WBS) elements and includes hardware, software, and services.

  • Format 2 provides the same data by the contractor's organization (functional or Integrated Product Team (IPT)) structure. Both Formats 1 and 2 include the current period and the cumulative to date Budgeted Cost for Work Scheduled (BCWS), Budgeted Cost for Work Performed (BCWP), Actual Cost of Work Performed (ACWP), their associated cost and schedule variances, the Budget at Completion (BAC) and Estimate at Completion (EAC) as well as the Variance at Completion (VAC).

  • Format 3 provides the budget baseline plan against which performance is being measured as well as any changes during the reporting period.

  • Format 4 provides staffing forecasts for correlation with the Estimate at Completion by the same organizational elements reported in Format 2.

  • Format 5 is a narrative report used to explain significant cost and schedule variances reported in Format 1, other identified contract problems and topics, uses of Management Reserve and Undistributed Budget, an explanation of any significant shifts in the budget baseline reported on Format 3, and to provide technical, schedule and cost impacts based upon root cause analyses, corrective action plans and the anticipated results from those corrective action plans. Other explanations provided on Format 5 are the differences between the Best Case, Worst Case and Most Likely EACs. Format 5 also provides the contractor's project manager an opportunity to address the overall health of the contract.

  • Format 6 is an electronic file of the contractor's Integrated Master Schedule with status shown as of the report date. Unless otherwise specified in the Contract Data Requirements List, the file is submitted in the contractor's own format.

  • Format 7 is an annual report in the contractor's electronic file format. It consists of the historical, time-phased actual costs (ACWP) plus future time-phased Estimate to Complete (ETC) values for all of the reported WBS elements of Format 1. The total of the time-phased costs must reconcile with Format 1, Block 8, Column (15), and the Estimate at Completion for the same reporting period.

Back to Glossary

/* request consultation forms JS */